Structure Access 21 State
General Information & Support
- View AT&T Structure Access guidelines
- Contact the AT&T Structure Access Team
- Access the AT&T Facility Portal
- AT&T Facility Portal Support
Account & Billing Management
- Add, update, or remove authorized contacts for my company
- View the current AT&T Structure Access rates
- Access and view my Structure Access billing
Agreements & Company Changes
- Negotiate a new Structure Access Agreement
- Amend my existing Structure Access Agreement
- Assign my Structure Access Agreement and/or assets to another company
- Change my company's name on my existing agreement and/or within AT&T's systems
Structure Access Requests
Facility Portal (CA & NV only)
- Request AT&T pole or conduit records
- Submit an attachment request
- Submit a notification to overlash an existing attachment
- Submit a request to rebuild an existing attachment
- Access an AT&T manhole for maintenance or presurvey work
- Submit a request for an emergency conduit reservation
Request (non-Facility Portal)
- Request AT&T pole or conduit records
- Submit a standard attachment request
- Submit a One Touch Make Ready (OTMR) Structure Access attachment request
- Submit a notification to overlash an existing attachment
- Submit a request to rebuild an existing attachment
- Access an AT&T manhole for maintenance or presurvey work
- Submit a request for an emergency conduit reservation
- Request make ready for AT&T attachments on a non-AT&T owned pole
Notification to AT&T
- Notify AT&T of One Touch Make Ready (OTMR) construction start or completion affecting AT&T attachments on non-AT&T owned poles
- Invoke self-help remedy for make-ready work affecting AT&T attachments
- Notify AT&T of removal of attachments on AT&T owned pole(s)
Authorized Contractor Management
- View AT&T authorized contractors
- Become an AT&T authorized contractor
- View Attacher authorized contractors
- Add an Attacher authorized contractor
General Information & Support
View AT&T Structure Access guidelines
AT&T's Structure Access guideline documents are shown below:
Contact the AT&T Structure Access Team
Current contacts for the AT&T Structure Access Team can be found here: Points of Contact for Structure Access
Access the AT&T Facility Portal
The AT&T Facility Portal provides access to AT&T solely owned and jointly owned pole data in California and Nevada. This pole data is currently only available to the following groups: California Public Utilities Commission Staff, California state and local government officials, Major Pole Owners in California, and 3rd Party Attachers within California or Nevada (requires an active structure access agreement with AT&T).
If you meet the requirements listed above and would like to request access to the AT&T Facility Portal, please follow the process listed in the AT&T Facility Portal Access Instructions.
Additional information concerning the AT&T Facility Portal can be found below:
- Frequently asked questions: AT&T Facility Portal FAQ
- Security questions and AT&T's response: AT&T Facility Portal Security Questions and Response
- Glossary of terms: AT&T Facility Portal Glossary
AT&T Facility Portal Support
Requests for support for the AT&T Facility Portal and the associated processes should be directed as follows:
- Facility Portal access issues: Use the chat support feature located on the AT&T Business Center if you have access to the AT&T Facility Portal but are having issues logging in.
- Request submittal process: Reach out to the appropriate contact listed in the Points of Contact for Structure Access.
- Technical issues: Submit an email request for help to ASAC Support explaining the issue that you are needed help with.
- Field descriptions: AT&T Facility Portal Field Descriptions Job Aid
Structure Access Requests
Request AT&T pole or conduit records
- Pole information - Facility Portal Pole Information Report Job Aid
- Conduit information - Facility Portal Conduit Information Request Job Aid
Submit an attachment request
The structure access process starts when an Attaching Party notifies AT&T of its wish to access AT&T's structure.
The following table lists various types of information that an Attaching Party may be required to provide:
Pole |
---|
All drawings or maps that provide details for the location of the work to be performed, the type of work being done, and any schematics/details of facilities being placed. |
Municipality and street names/addresses, primary & subsequent placement paths, identity of subject AT&T poles including pole number(s) and latitude/longitude. |
Location, type, size, weight, height of attachment(s) and equipment being placed to include ancillary equipment, splices, and cable loops. |
Existing attachment(s) and height(s) for any attachment(s) on the pole(s). |
All make-ready work required by any existing attacher. |
Attaching Party point of contact and telephone number/email along with company doing work. |
Conduit |
---|
All drawings or maps that provide details for the location of the work to be performed, the type of work being done, and any schematics/details of facilities being placed. |
Identification of start and end of work, i.e. MH or bldg. number, street address, distance to next MH. |
Cable outside diameter (OD), cable type (copper, fiber, coaxial), number of tubes, voltage to ground and maximum current of any conductor, spare ducts/innerducts. |
Splices and/or how much slack to be placed in a MH. |
Make-ready work required with details, including knockouts or core boring required. |
Attaching Party point of contact and telephone number/email along with company doing work. |
Pole Attachment Request
Conduit Attachment Request
Submit a notification to overlash an existing attachment
Submit a request to rebuild an existing attachment
Access an AT&T manhole for maintenance or presurvey work
Submit a request for an emergency conduit reservation
Request AT&T pole or conduit records
- Complete the Records Review Request (REC-REV-002).
- Submit the completed form to the appropriate contact listed in the Points of Contact for Structure Access.
Submit a standard attachment request
The structure access process starts when an Attaching Party notifies AT&T of its wish to access AT&T's structure.
The Attaching Party should complete all required fields on the application form(s), provide all the applicable information required on the form, and submit the request to the Local Structure Access Team.
The following table lists various types of information that an Attaching Party may be required to provide:
Pole |
---|
All drawings or maps that provide details for the location of the work to be performed, the type of work being done, and any schematics/details of facilities being placed. |
Municipality and street names/addresses, primary & subsequent placement paths, identity of subject AT&T poles including pole number(s) and latitude/longitude. |
Location, type, size, weight, height of attachment(s) and equipment being placed to include ancillary equipment, splices, and cable loops. |
Existing attachment(s) and height(s) for any attachment(s) on the pole(s). |
All make-ready work required by any existing attacher. |
Attaching Party point of contact and telephone number/email along with company doing work. |
Conduit |
---|
All drawings or maps that provide details for the location of the work to be performed, the type of work being done, and any schematics/details of facilities being placed. |
Identification of start and end of work, i.e. MH or bldg. number, street address, distance to next MH. |
Cable outside diameter (OD), cable type (copper, fiber, coaxial), number of tubes, voltage to ground and maximum current of any conductor, spare ducts/innerducts. |
Splices and/or how much slack to be placed in a MH. |
Make-ready work required with details, including knockouts or core boring required. |
Attaching Party point of contact and telephone number/email along with company doing work. |
Pole Attachment Request
- Prior to performing the make-ready survey and submitting a pole attachment request, the Attaching Party should obtain AT&T pole records for the area of interest by submitting a request for AT&T pole records.
- Complete the Application (APP-002).
- Complete the Pole Data Sheet (POLE-DATA-003) for all poles associated with the request.
- Refer to the Pole Data Sheet Instructions document for instructions on completing the Pole Data Sheet.
- Refer to the Pole Data Sheet Instructions document for instructions on completing the Pole Data Sheet.
- Complete pole loading for each pole associated with the request. Files should contain only 1 pole per file (i.e. do not lump all poles into a single file) and each file name should start with "PLA-" (e.g. PLA-Pole1-126 Main St.pdf)
- Create a map of the proposed path that includes all poles associated with the request.
- Submit all completed documents listed above to the Local Structure Access Team.
Conduit Attachment Request
- Follow the Manhole Access process to perform the required make-ready survey of the affected manholes.
- Complete the Application (APP-002).
- Complete the Conduit Data Sheet (COND-001).
- Complete a Manhole Detail Requirements (MHDET-001) sheet for each manhole associated with the request.
- Complete a Manhole/Vault Access (MHACC-002) for each manhole associated with the request that will require entry for facility placement.
- If the request proposes core boring a manhole, complete the Request to Core Bore or Modify Manhole (CORE-002) form for each manhole where you are proposing to core bore or modify the manhole.
- Create a map of the proposed path that includes all manholes associated with the request.
- Submit all completed documents identified in items 2-7 above to the Local Structure Access Team.
Submit a One Touch Make Ready (OTMR) Structure Access attachment request
If you do not currently have an agreement with the OTMR provisions and would like to amend your agreement to have them added, follow the Structure Access Agreement amendment process.
The structure access process starts when an Attaching Party notifies AT&T of its wish to access AT&T's structure.
The Attaching Party should complete all required fields on the application form(s), provide all the applicable information required on the form, and submit the request to the Local Structure Access Team.
The following table lists various types of information that an Attaching Party may be required to provide:
Pole |
---|
All drawings or maps that provide details for the location of the work to be performed, the type of work being done, and any schematics/details of facilities being placed. |
Municipality and street names/addresses, primary & subsequent placement paths, identity of subject AT&T poles including pole number(s) and latitude/longitude. |
Location, type, size, weight, height of attachment(s) and equipment being placed to include ancillary equipment, splices, and cable loops. |
Existing attachment(s) and height(s) for any attachment(s) on the pole(s). |
All make-ready work required by any existing attacher. |
Attaching Party point of contact and telephone number/email along with company doing work. |
- Prior to performing the make-ready survey and submitting a pole attachment request, the Attaching Party should obtain AT&T pole records for the area of interest by submitting a request for AT&T pole records.
- View the current list of AT&T authorized contractors or Attacher authorized contractors to identify contractors approved to perform the proposed work associated with the request.
- To add an authorized contractor to the Attacher authorized contractor list, refer to the Add an Attacher authorized contractor section.
- To add an authorized contractor to the Attacher authorized contractor list, refer to the Add an Attacher authorized contractor section.
- Complete the Application (APP-002) and indicate that the request is for OTMR.
- Complete the Pole Data Sheet (POLE-DATA-003) for all poles associated with the request.
- Refer to the Pole Data Sheet Instructions document for instructions on completing the Pole Data Sheet.
- Refer to the Pole Data Sheet Instructions document for instructions on completing the Pole Data Sheet.
- Complete pole loading for each pole associated with the request. Files should contain only 1 pole per file, i.e. do not lump all poles into a single file.
- Create a map of the proposed path that includes all poles associated with the request.
- Submit all completed documents listed above to the Local Structure Access Team.
Once permitted by AT&T to attach and perform the approved One Touch Make Ready on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party must provide notification of the start date and completion date of all make-ready work performed on AT&T attachments as follows:
- Prior to performing the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Start date ATT Poles form and submit it to the issuer of the permit.
- Upon completion of the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Complete date ATT Poles form and submit it to the issuer of the permit.
Submit a notification to overlash an existing attachment
- Complete the Notification to Overlash/Rebuild (NOR) form.
- If the form indicates pole loading is required, complete pole loading for each pole associated with the notification. Files should contain only 1 pole per file, i.e. do not lump all poles into a single file.
- Create a map of the proposed path that includes all poles associated with the notification.
- Submit all completed documents listed above to the Local Structure Access Team.
Submit a request to rebuild an existing attachment
- Complete the Notification to Overlash/Rebuild (NOR) form.
- If the form indicates pole loading is required, complete pole loading for each pole associated with the notification. Files should contain only 1 pole per file, i.e. do not lump all poles into a single file.
- Create a map of the proposed path that includes all poles associated with the notification.
- Submit all completed documents listed above to the Local Structure Access Team.
Access an AT&T manhole for maintenance or presurvey work
- Complete the Manhole/Vault Access (MHACC-002) form.
- Create a map of the proposed path that includes all manholes/vaults associated with the request.
- Submit all completed documents listed above to the Local Structure Access Team.
Submit a request for an emergency conduit reservation
- Complete the Request for Emergency Conduit Reservation (EMER-002) form.
- Complete a Manhole/Vault Access (MHACC-002) for each manhole associated with the request that will require entry for facility placement.
- If the request proposes core boring a manhole, complete the Request to Core Bore or Modify Manhole (CORE-002) form for each manhole where you are proposing to core bore or modify the manhole.
- Create a map of the proposed path that includes all manholes associated with the request.
- Submit all completed documents listed above to the Local Structure Access Team.
Request make ready for AT&T attachments on a non-AT&T owned pole
To request make ready be performed for AT&T attachments on a non-AT&T owned pole, provide your name, address, phone number, email address, and a brief desciprition of the work requested to the appropriate contact listed below:
State | Phone | |
---|---|---|
AL, FL, GA, IL, IN, KY, LA, MI, MS, NC, OH, SC, TN, WI | gen1361@att.com | 888-901-2779 |
CA, NV | g24685@att.com | 888-964-7072 |
AR, KS, MO, OK, TX | g12599@att.com | 888-964-7072 |
Notify AT&T of One Touch Make Ready construction start or completion affecting AT&T attachments on non-AT&T owned poles
Upon receiving an OTMR permit from the pole owner to perform make-ready construction affecting AT&T attachments on a non-AT&T owned or jointly owned pole, Attaching Party must provide notification of the start date and completion date of all make-ready work performed on AT&T attachments as follows:
- Prior to performing the permitted make-ready affecting AT&T attachments, Attaching Party will complete the AP Notification of MR Construction Start date FO Poles form and submit it to the issuer of the permit.
- Upon completion of the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Complete date FO Poles form and submit it to the Local Structure Access Team.
Invoke self-help remedy for make-ready work affecting AT&T attachments
When an Attaching Party elects to invoke the self-help remedy for make-ready work affecting AT&T attachments, Attaching Party must provide notification of the start date and completion date of all make-ready work performed on AT&T attachments as follows:
- AT&T Owned or Jointly Owned Poles
- Prior to performing the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Start date ATT Poles form and submit it to the issuer of the permit.
- Upon completion of the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Complete date ATT Poles form and submit it to the issuer of the permit.
- Prior to performing the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Start date ATT Poles form and submit it to the issuer of the permit.
- Foreign Owned (FO), Non-AT&T Owned Poles
- Prior to performing the permitted make-ready affecting AT&T attachments, Attaching Party will complete the AP Notification of MR Construction Start date FO Poles form and submit it to the issuer of the permit.
- Upon completion of the permitted make-ready on AT&T attachments located on an AT&T pole (or AT&T owned grade on a jointly owned pole), Attaching Party will complete the AP Notification of MR Construction Complete date FO Poles form and submit it to the Local Structure Access Team.
- Prior to performing the permitted make-ready affecting AT&T attachments, Attaching Party will complete the AP Notification of MR Construction Start date FO Poles form and submit it to the issuer of the permit.
Notify AT&T of my removal of attachment(s)
When Attaching Party no longer intends to occupy space in or on AT&T's structure, Attaching Party must provide written notification to AT&T by completing Notification of Surrender or Modification of Attachment License form and submit it to the Local Structure Access Team.
Contacts | top | ||
---|---|---|---|
![]() |
Points of Contact |
Guidelines | top | ||
---|---|---|---|
Revised: 07/31/19 |
![]() |
Guidelines for Boxing and Bracketing | |
Revised: 01/03/25 |
![]() |
Annual/Semi-Annual Invoice Retrieval Job Aid | |
Revised: 10/31/23 |
![]() |
Structure Access Application Process | |
Revised: 05/29/24 |
![]() |
Structure Access Guidelines |
Forms | top | ||
---|---|---|---|
Revised: 03/24/25 |
![]() |
Assignment Request Form | |
Revised: 02/24/25 |
![]() |
Structure Access Negotiations Request Form | |
Revised: 08/21/25 |
![]() |
Application (APP-002) | |
Revised: 03/15/21 |
![]() |
Conduit Data Sheet (COND-001) | |
Revised: 10/17/23 |
![]() |
Letter of Authorization for Applications, Record Reviews, Billing & Notices (LOA) | |
Revised: 03/15/21 |
![]() |
Manhole Detail Requirements (MHDET-001) | |
Revised: 03/15/24 |
![]() |
Manhole/Vault Access (MHACC-002) | |
Revised: 03/23/22 |
![]() |
Notification of Surrender or Modification of Attachment License (SUR-MOD) | |
Revised: 08/11/25 |
![]() |
Notification to Overlash/Rebuild (NOR) | |
Revised: 03/15/21 |
![]() |
Pole Data Sheet (POLE-DATA-003) | |
Revised: 08/01/18 |
![]() |
Pole Data Sheet Instructions | |
Revised: 05/29/24 |
![]() |
Records Review Request (REC-REV-002) | |
Revised: 03/15/21 |
![]() |
Request for Emergency Conduit Reservation (EMER-002) | |
Revised: 03/15/21 |
![]() |
Request to Core Bore or Modify Manhole (CORE-002) |
Attacher Notification of Construction Start and Completion forms | top | ||
---|---|---|---|
Revised: 12/07/21 |
![]() |
AP Notification of MR Construction Complete date ATT Poles | |
Revised: 12/07/21 |
![]() |
AP Notification of MR Construction Complete date FO Poles | |
Revised: 12/07/21 |
![]() |
AP Notification of MR Construction Start date ATT Poles | |
Revised: 12/07/21 |
![]() |
AP Notification of MR Construction Start date FO Poles |
FCC 18-111 Order Forms | top | |||
---|---|---|---|---|
![]() |
Please Note: | |||
* These forms are only to be used if an Attaching Party has an executed Category B or FCC Agreement and wishes to invoke any part of the FCC 18-111 Order. An Attaching Party wishing to execute a new, or amend an existing, Structure Access agreement to include these provisions must submit a request per the New Agreement Negotiation Process listed on this page. | ||||
Revised: 03/07/25 |
![]() |
Application (APP-002) | ||
Revised: 07/30/24 |
![]() |
Applicant Submission of Authorized Contractor Instructions | ||
Revised: 07/30/24 |
![]() |
Applicant Submission of Authorized Contractor | ||
Revised: 07/12/23 |
![]() |
Notification to Overlash/Rebuild (NOR) |
AT&T Authorized Contractor List | top | ||
---|---|---|---|
Revised: 07/03/25 |
![]() |
Civil Engineering for conduit/pole attachment | |
Revised: 07/03/25 |
![]() |
Conduit cable/duct placement | |
Revised: 07/03/25 |
![]() |
Conduit or Pole attachment pre-construction survey | |
Revised: 07/03/25 |
![]() |
Pole attachment make-ready work |
Attacher Authorized Contractors Within the Communications Space | top | ||
---|---|---|---|
Revised: 06/30/25 |
![]() |
POLE-MAKE-READY-IN-COMM-SPACE | |
Revised: 06/27/25 |
![]() |
POLE-SURVEY |
Attacher Authorized Contractors Above the Communications Space | top | ||
---|---|---|---|
Revised: 04/30/25 |
![]() |
Pole Make ready Above Comm Space |
Rates and Optional Agreements | top | ||
---|---|---|---|
![]() |
Rates and Optional Agreement |
Regional | top | ||
---|---|---|---|
Revised: 07/31/19 |
![]() |
West-AT&T CA Conduit Mapping Protocol | |
Revised: 07/31/19 |
![]() |
West-AT&T California Structure Access Protocol Addendum, | |
![]() |
West-California General Order | ||
Revised: 05/05/20 |
![]() |
West-AT&T CA Max Grade\Conduit Map Req Form | |
Revised: 05/05/20 |
![]() |
West-AT&T CA Non-Disclosure Agreement | |
Revised: 08/21/20 |
![]() |
West – Make Ready Form | |
Revised: 09/29/20 |
![]() |
West – Applicant Notice |